Kelly Brothers (KBI) demolished the existing 2,900 sq. ft. fishing pier and constructed a 10’ x 160’ long access dock with a 50’ x 18’ terminal platform, and a five-step mooring platform. All of the demolition, material staging, and reconstruction work was completed off of KBI’s 30’ x 120’ barge due to limited access to the jobsite via land. The new structure was constructed to endure the South Florida elements with large 4” x 16” cap boards, 3” x 12” stringers, and Durasleeve wrapped 12” wood pilings. In addition, “Mother Nature Resistant” WearDeck composite decking was used for the deck and handrails. The entire project took nine weeks to complete.
Location:
763 South Harbor Drive
Boca Grande, FL 33921
Owner:
Boca Bay Master Association, Inc.
Engineer:
Hans Wilson and Associates
3584 Exchange Avenue
Suite B
Naples, FL 34104-3732
Contract:
Prime
Date Completed:
November 2019