Marina Jack, Phase I through IV,
Sarasota, FL
Kelly Brothers worked on multiple phases of seawall and dock system improvements with this prestigious marina complex. Work included demolition of the concrete dock system and installation of over 7,200 sq. ft. of Bellingham Floating Docks. Also installed were twenty (20) 18” square x 40’ long FDOT concrete piles and thirteen (13) 12” x 35’ long timber mooring piles.
Location:
2 Marina Plaza
Sarasota, FL
Owner:
Marina Jack, Inc.
Engineer:
Bellingham Marine
1813 Dennis Street
Jacksonville, FL 32204
Contract:
Prime
Date Completed:
Phase I: December 2004
Phase II: February 2006
Phase III: December 2008
Phase IV: July 2012